The internal audit is where you check your own ISMS before anyone else does. Clause 9.2 of ISO/IEC 27001:2022 asks whether the ISMS conforms to your own requirements and to the standard, and whether it is effectively implemented and maintained.

Below: what 9.2 actually requires, a working checklist for clauses 4 to 10 and a sample of Annex A controls, and what to do with the findings afterward.

What clause 9.2 requires

The standard does not say who must audit. A small organization can use a trained colleague from another team, or an outside auditor, as long as they are not auditing their own work. ISO 19011 is the general guidance standard for auditing management systems if you want more on method.

Timing: certification bodies generally expect to see at least one completed internal audit and management review before the Stage 2 audit. Ask yours what they expect for your first cycle.

Before the audit

The checklist: clauses 4 to 10

For each line, ask for the record that proves it, not a description of it. “We do that” is not evidence; the review sign-off, the ticket or the training log is.

Clause 4: Context

  • 4.1☐ Internal and external issues relevant to the ISMS have been identified, and are still current.
  • 4.2☐ Interested parties, their relevant requirements, and which of those requirements the ISMS addresses are recorded.
  • 4.3☐ The ISMS scope is documented, including boundaries, interfaces and dependencies.
  • 4.4☐ The ISMS processes and how they interact are established and maintained.

Clause 5: Leadership

  • 5.1☐ Top management can show its commitment: resources provided, ISMS integrated into business processes, policy and objectives set.
  • 5.2☐ The information security policy exists, is documented, communicated within the organization and available to interested parties as appropriate.
  • 5.3☐ Roles, responsibilities and authorities for the ISMS are assigned and communicated.

Clause 6: Planning

  • 6.1.2☐ The risk assessment process is documented, with risk acceptance criteria, and produces consistent, comparable results.
  • 6.1.3☐ The risk treatment plan exists, risk owners approved it and accepted the residual risks, and the Statement of Applicability matches it.
  • 6.2☐ Information security objectives are measurable where practicable, with plans saying what, who, by when and how results are evaluated.
  • 6.3☐ Changes to the ISMS are carried out in a planned way.

Clause 7: Support

  • 7.1-7.2☐ Resources are in place, and competence of people doing ISMS work is determined and evidenced (training, experience, qualifications).
  • 7.3-7.4☐ Staff know the policy, their contribution, and what happens if they do not follow it. Internal and external communication is planned.
  • 7.5☐ Documented information is identified, reviewed, approved, version-controlled and protected.

Clause 8: Operation

  • 8.1☐ Processes are planned and controlled, including outsourced processes and planned changes.
  • 8.2☐ Risk assessments are performed at planned intervals and after significant changes, and the results are retained.
  • 8.3☐ The risk treatment plan is being implemented, and the results are retained.

Clause 9: Performance evaluation

  • 9.1☐ You have decided what to monitor and measure, how, when and by whom, and the results are recorded and evaluated.
  • 9.2☐ The previous internal audit was completed as planned and its findings were followed up.
  • 9.3☐ Management reviews took place with the required inputs, and their decisions and actions are recorded.

Clause 10: Improvement

  • 10.1☐ There is evidence of continual improvement, not just maintenance.
  • 10.2☐ Nonconformities are corrected, root causes are analyzed, corrective actions are taken and their effectiveness is reviewed, with records kept.

The checklist: a sample of Annex A controls

You do not need to audit all 93 controls every time, but over your audit program every applicable control should be covered. Take the sample from your SoA. These are common starting points:

Recording findings

Each finding should state the requirement, what you found, and the evidence you looked at. Typical categories are a conformity, a nonconformity (a requirement is not met), an observation (not yet a nonconformity, but heading there), and an opportunity for improvement. ISO 27001 itself does not define “major” and “minor”; certification bodies use those grades, and many organizations borrow them internally.

From nonconformity to corrective action (clause 10.2)

For every nonconformity, clause 10.2 asks you to react (correct it and deal with the consequences), find the cause, check whether it could happen elsewhere, take corrective action, and review whether that action worked. Keep records of the nonconformity, what you did, and the result. A nonconformity closed without an effectiveness check is a common audit finding in its own right.

Feeding the management review (clause 9.3)

Audit results are a required input to management review, along with the status of nonconformities and corrective actions, monitoring results, risk assessment results and the status of the risk treatment plan. Report the audit to the relevant managers when it closes, then bring the summary and the open actions to the next review so leadership can decide what to change.

How GapLedger handles internal audits

In GapLedger, each internal audit records the framework, the planned date, the scope, the auditor and the auditor's qualifications, and moves from planned to completed with a summary. Findings are logged as conformity, nonconformity, observation or opportunity for improvement, and a nonconformity or observation becomes a tracked nonconformity in one step, with corrective actions, owners, due dates and an effectiveness note. The management review form then opens with a snapshot of open nonconformities, open corrective actions, open and high risks, and the last completed audit. All of it goes into the audit pack PDF for your certification auditor.

See how a first ISO 27001 audit goes, step by step, or read the ISO 27001 software page for the rest of the ISMS.

Start your 7-day trial

Card required; cancel before day 7 and you won't be charged. $500/mo after trial, or $5,400/yr and save 10%.